Integration Timeline

Device TypeCommon DevicesIntegration ProtocolIntegration TimelineRemarks
Power Conversion System (PCS)Mainstream PCS Brands
(Standard Protocol)
Modbus RTU/TCP
CAN
3 days1. Requires register debugging and control logic verification
Mainstream PCS Brands
(Non-standard Protocol)
IEC 6185010–20 days
  1. Requires modeling, ICD import, and system integration testing
  2. New protocol stack development is relatively complex and takes longer for the first migration
  3. The timeline can be reduced by 50% for subsequent projects
Niche / New PCS Brands
(Non-standard Protocol)
Proprietary Custom Protocol10–15 days
  1. Requires register debugging and control logic verification
  2. Protocols from niche brands may be less mature, resulting in longer debugging time
Battery Management System (BMS)Mainstream BMSModbus RTU/TCP
CAN
3 days1. Standard data integration
Customized BMSProprietary Protocol3–5 days1. Requires custom integration development
PV InverterString / Central InverterModbus RTU/TCP2 days1. Standard data integration
Energy MeterMulti-function Energy MeterModbus RTU/TCP
DL/T645
1 day1. Standard data integration
Temperature Control SystemLiquid Cooling UnitModbus RTU/TCP2 days1. Standard data integration
Air ConditionerModbus RTU/TCP2 days1. Standard data integration
EV ChargerMainstream EV Chargers / Charging StationsModbus RTU/TCP4 days1. Standard data integration and power scheduling
Niche / New Brands EV ChargersModbus RTU/TCP6–8 days1. Standard data integration and power scheduling
Microgrid / Off-grid ApplicationsPure Microgrid (VF/VSG)Modbus RTU/TCP10 days1. Includes microgrid forming, islanding, frequency and voltage regulation logic
Grid-connected / Off-grid Switching
Circuit Breaker / ATS / STS
Modbus / Dry Contact10 days1. Includes interlocking and mode switching logic; high control complexity and mostly customized requirements
Diesel GeneratorGenerator SetModbus RTU10 days1. Includes start/stop control and power matching
Grid DispatchIndustrial Park / Grid Control CenterIEC 10420–30 days
  1. Upstream integration with station-level control systems
  2. First protocol migration requires longer development time
  3. The timeline can be reduced by 50% for subsequent projects
Third-party PlatformCloud Platform, Energy Management SystemMQTT / HTTP20–30 days
  1. Direct cloud integration is not recommended due to difficulties in after-sales support and upgrades
  2. Cloud-to-cloud integration is recommended
Strategy AlgorithmsCustom Charge/Discharge Strategy//1. Existing standard algorithms generally do not require additional development
Peak-Valley Arbitrage//
Demand Management//
Reverse Power Protection//
Renewable Energy Utilization//
Dynamic Transformer Capacity Expansion//
Custom Strategy//1. Custom algorithms or other complex non-standard applications require separate evaluation and discussion